1. •   Stonescapes
  2. •   3M Colorquartz
  3. •   Stamped Concrete
  4. •   Spray Deck

 

 

Stonescapes
The Stonescape finish is colorfast. It will stay truer in color than any other pool finish available on the market today.

3M Colorquartz
An exposed aggregate finish made of tough ceramic coated quartz granules mixed with white cement. Each individual quartz granule undergoes a proprietary 3M process that bonds permanent inorganic pigments to the quartz.

Stamped Concrete
Stamped concrete is concrete that is patterned to resemble brick, slate, flagstone, stone, tile- and even wood.

Spray Deck
Spray-Deck has a smooth non-skid surface, which is also resistant to mildew, extremely durable, very easy to maintain, and very affordable.






 



CONSTRUCTION GUIDE


This guide is provided to help you have a pleasant experience during a commonly frustrating
process known as construction.

We have found that the most common cause of frustration is not knowing what to expect.
We hope that this guide will assist you in understanding the swimming pool construction
process.

 

THE POOL BUILDING PROCESS

Prior to excavation, all building permits must be obtained and on site (if applicable).

All scheduled dates are tentative and subject to change due to:

        Each phase must be completed and approved by the superintendent before scheduling
next phase.

        Adverse weather conditions, such as wind or rain, can delay steel, shotcrete, deck and
plaster. If this occurs, we reschedule for the next available date.

        Revisions to the final approved plan will cause delays.

        There may be days when no worked is performed on site. This is due to the specialized
nature of Laguna's crews and scheduling them in and out.

 

 

________________________________________________________________________________



 

TABLE OF CONTENTS

3      ....  Layout

4            Excavation

5            Caliche

6            Plimbing

7            Steel

8            Electrical

9            Pre-Gunite Inspection

10          Shotcrete

11          Tile & Rock Work / Waterfalls

12          Clean Up and Deck

13          Safety Barriers

14          Final Inspection

15          Plaster / Pebble

16          Start Up & Orientation

17          Final Walk / Punch List


 


____________________________________________________________________________

 

 

 

LAYOUT

        Pool shape is spray painted on the ground per plan.

        Superintendent checks the layout for accuracy and the lot thoroughly for construction
conflicts.

        If the homeowner wishes to make changes, now is the time. It is much easier to erase
paint and respray, than to fill and re-dig a hole.

Back to Table of Contents

 

______________________________________________________________________________

 

 

 

EXCAVATION

        The pool is dug.

        Mounds are formed at the location of steps.

        Dump trucks full of dirt are very heavy. Concrete may break if they cross over it to
obtain backyard access.

        Trucks and tractors will make a mess of the access area.  This can not be avoided.
The access area will be cleaned when pool construction is completed.

Back to Table of Contents

 

______________________________________________________________________________

 

 

 

CALICHE

        If rock or unusual soil conditions are encountered during excavation, a hard dig could
result.

        The superintendent will inspect and verify it is a hard dig.

        If caliche is found, additional fees may be charged to continue digging and remove the caliche.

        Outside bids for caliche removal are welcome, but will further delay construction.

Back to Table of Contents

 

______________________________________________________________________________

 

 

 

PLUMBING

        All plumbing and pool equipment are installed.

        The system is pressurized and checked for leaks.

        Any plumbing leaks visible by a wet area or drip are repaired.

        Installation of any gas lines (if applicable).

        The final gas hook up, connecting the stub to the meter, can only be performed by
Southwest Gas. The homeowner is required to make an appointment and there is no
charge for this service.

Back to Table of Contents

 

________________________________________________________________________________

 

 

 

STEEL

        Steel bars (rebar) are placed in a grid-like pattern throughout the pool.

        Steel is placed on top of the mounds for the steps.

        Preliminary electrical inspection is scheduled.

        Steel tied to follow structural engineering calculations, every pool is different based upon depths and configuration

Back to Table of Contents

 

________________________________________________________________________________

 

 

 

ELECTRICAL

        Install light niche and rough electrical and bonding is performed. National codes require
all metal within 5' of the water's edge is bonded. Bonding is a copper wire connected to
all metal and is similar to grounding.

        If someone other than Laguna is installing your wrought iron, make sure they perform
the bonding sufficiently.

        Be sure to leave all breakers off.

        Pre-gunite (shotcrete) inspection is scheduled.

Back to Table of Contents

 

________________________________________________________________________________

 

 

 

PRE-GUNITE INSPECTION

        A city building inspector will check the electrical, plumbing and steel for proper
bonding and to ensure the pool is ready for shotcrete.

        Once inspection is approved, shotcrete will be scheduled.

 

Back to Table of Contents

 

________________________________________________________________________________

 

 

 

SHOTCRETE

        Concrete is sprayed to create the pool shell and the steps are formed.

        Spray shotcrete with water thoroughly 2-3 times per day for the next 7 days.

        Keeping the concrete damp enables it to cure properly and reach full strength integrity.
Don't worry if water collects on the bottom while curing.

        Shrinkage cracks are normal and not structural in nature. Proper watering on the first day minimizes shrinkage cracks, although it probably will not prevent them.

        Ensure all color selections for tile, grout, flagstone, deck and interior finish are approved.

 

Back to Table of Contents

 

________________________________________________________________________________

 

 

 

TILE & ROCK WORK/WATERFALLS

        Waterfall or other rock work is scheduled. Superintendent meets with homeowner to
discuss what to expect.

        A row of 6” wide tile is installed under deck placement and where specified per plan.

        Unless specifically requested, we do not place tile on rolled beams.

        Pre-deck inspection is scheduled.

        Upon approval, clean up and deck are scheduled.

        Reminder – barrier requirements must be met.


Back to Table of Contents

 

________________________________________________________________________________

 

 

 

CLEAN UP AND DECK

        Prepare area for deck and place forms around edges. Check to ensure no changes
are necessary.

        Concrete is poured and deck is sprayed with chosen color.

        Clean up around pool and yard is completed.

        DO NOT WALK ON WET CEMENT FOR AT LEAST 24 HOURS. 
Keep children and pets out of the area for 36 hours.

        Schedule masonry if applicable.

        Code gate if applicable.

        Schedule headset for in-floor systems.

        Schedule superintendent pre-final inspection.

Back to Table of Contents

 

________________________________________________________________________________

 

 

 

SAFETY BARRIERS

Safety codes are governed by the city to prevent children unsupervised access to the
pool area. Typical barrier requirements are:

-      Minimum 5' high block wall fence around the yard.

-      An outward opening gate to yard that is self-closing and self-latching.

-      All windows opening to yard have locks 54” high to prevent windows from

                opening more than 4”.

-    Sliding glass windows must be self-closing and self-latching with the handle         

                54” high.

-     Doors opening to the yard must have a lock 54” high.

-     Doors opening to the pool area must have door alarms.

        Laguna can be contracted to obtain current barrier codes and bring residence to
compliance, otherwise it is your responsibility.

        A final or pre-plaster inspection is scheduled.

Back to Table of Contents

 

________________________________________________________________________________

 

 

 

FINAL INSPECTION

        City inspector checks all safety barriers.

        You must be home for this inspection.

        Superintendent will check pool with you to ensure everything is correct.

Back to Table of Contents

 

________________________________________________________________________________

 

 

 

PLASTER/PEBBLE

       A 1/2” thick layer of plaster or pebbled finish, depending on your contract, is sprayed and troweled onto the shotcrete surface.

        Immediately after finish is applied, water begins filling the pool and/or spa.

        Continue filling until water level is halfway up the tiles.

        For plaster finish pools, begin brushing 3-5 times per day once the pool is full.

Back to Table of Contents

________________________________________________________________________________

 

 

 

START UP & ORIENTATION

        When your pool is full, contact the office to schedule your start up.

        Our technician will come out to get the pool up and running.

        Do not attempt to turn on the pool yourself.

        Homeowner is responsible for start up chemicals.

        Technician will orient you on equipment functionality and maintenance.



Back to Table of Contents

________________________________________________________________________________

 

 

 

FINAL WALK/PUNCH LIST

        We will walk the project with you to note any unfinished items or necessary repairs.

        A date for repairs will be scheduled with our office.

HAVE FUN ENJOYING YOUR NEW LAGUNA POOL!!



Back to Table of Contents