This
guide is provided to help you have a pleasant experience during a commonly
frustrating
process known as construction.
We have found that the most common cause of frustration is
not knowing what to expect.
We hope that this guide will assist you in understanding
the swimming pool construction
process.
________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________
LAYOUT
•
Pool shape is spray painted on the ground per plan.
•
Superintendent checks the layout for accuracy and the lot thoroughly for construction
conflicts.
•
If the homeowner wishes to make changes, now is the time. It is much easier to erase
paint and respray, than to fill and re-dig a hole.
Back to Table of Contents |  |
_______________________________________________________________________________________________________________________________ |
EXCAVATION
•
The pool is dug.
•
Mounds are formed at the location of steps.
• Dump trucks full of dirt are very heavy. Concrete may break if they cross over it to obtain backyard access.
•
Trucks and tractors will make a mess of the access area. This can not be avoided.
The access area will be cleaned when pool construction is completed.
Back to Table of Contents
|  |
_______________________________________________________________________________________________________________________________ |
CALICHE
• If rock or
unusual soil conditions are encountered during excavation, a hard dig could result.
•
Thesuperintendent will inspect and verify it is a hard dig.
•
If caliche is found, additional fees may be charged to continue digging and remove the caliche.
•
Outside bids for caliche removal are welcome, but will further delay construction.
Back to Table of Contents
|  |
_______________________________________________________________________________________________________________________________ |
PLUMBING
• All plumbing and pool equipment are installed. • The system is
pressurized and checked for leaks.
• Any plumbing leaks visible by a wet area or drip are repaired.
• Installation of any gas lines (if applicable).
• The final gas hook up, connecting the stub to the meter, can only be performed by Southwest Gas. The homeowner is required to make an appointment and there is no charge for this service.
Back to Table of Contents
|  |
_______________________________________________________________________________________________________________________________ |
STEEL
• Steel bars (rebar) are placed in a grid-like pattern throughout the pool.
• Steel is placed on top of the mounds for the steps.
• Preliminary electrical inspection is scheduled.
• Steel tied to follow structural engineering calculations, every pool is different based upon depths and configuration
Back to Table of Contents |  |
_______________________________________________________________________________________________________________________________ |
ELECTRICAL
• Install light niche and rough electrical and bonding is performed.
National codes require
all metal within 5' of the water's edge is bonded.
Bonding is a copper wire connected to
all metal and is similar to grounding.
• If someone other than Laguna is installing your wrought iron, make sure
they perform
the bonding sufficiently.
• Be sure to leave all breakers off.
• Pre-gunite (shotcrete)
inspection is scheduled.
Back to Table of Contents |  |
_______________________________________________________________________________________________________________________________ |
PRE-GUNITE INSPECTION
• A city building
inspector will check the electrical, plumbing and steel for proper
bonding
and
to ensure the pool is ready for shotcrete.
• Once inspection
is approved, shotcrete will be scheduled.
Back to Table of Contents
|  |
______________________________________________________________________________________________________________________________ |
SHOTCRETE
• Concrete is
sprayed to create the pool shell and the steps are formed.
• Spray shotcrete with water thoroughly 2-3 times per day for the
next 7 days.
• Keeping the
concrete damp enables it to cure properly and reach full strength integrity.
Don't worry if water collects on the bottom while curing.
• Shrinkage cracks
are normal and not structural in nature. Proper watering on the first day
minimizes shrinkage cracks, although it probably will not prevent them.
• Ensure all color
selections for tile, grout, flagstone, deck and interior finish are approved.
Back to Table of Contents
|  |
_______________________________________________________________________________________________________________________________ |
TILE & ROCK
WORK/WATERFALLS
• Waterfall or
other rock work is scheduled. Superintendent meets with homeowner to
discuss
what to expect.
• A row of 6”
wide tile is installed under deck placement and where specified per plan.
• Unless
specifically requested, we do not place tile on rolled beams.
• Pre-deck
inspection is scheduled.
• Upon approval,
clean up and deck are scheduled.
• Reminder –
barrier requirements must be met.
Back to Table of Contents
|  |
_______________________________________________________________________________________________________________________________ |
CLEAN UP AND DECK
• Prepare area for
deck and place forms around edges. Check to ensure no changes
are necessary.
• Concrete is
poured and deck is sprayed with chosen color.
• Clean up around
pool and yard is completed.
• DO NOT WALK ON
WET CEMENT FOR AT LEAST 24 HOURS.
Keep children and pets out of the area for 36 hours.
• Schedule masonry
if applicable.
• Code gate if
applicable.
• Schedule headset
for in-floor systems.
• Schedule
superintendent pre-final inspection.
Back to Table of Contents
|  |
_______________________________________________________________________________________________________________________________ |
SAFETY BARRIERS
Safety
codes are governed by the city to prevent children unsupervised access to the
pool area. Typical barrier requirements are:
- Minimum 5' high block wall fence around the yard.
- An outward opening gate to yard that is self-closing
and self-latching.
- All windows opening to yard have locks 54” high
to prevent windows from
opening more than 4”.
- Sliding glass windows must be self-closing and
self-latching with the handle
54” high.
- Doors opening to the yard must have a lock 54”
high.
- Doors opening to the pool area must have door alarms.
• Laguna can be
contracted to obtain current barrier codes and bring residence to
compliance,
otherwise it is your responsibility.
• A final or
pre-plaster inspection is scheduled.
Back to Table of Contents
|  |
_______________________________________________________________________________________________________________________________ |
FINAL INSPECTION
• City inspector
checks all safety barriers.
• You must be home
for this inspection.
• Superintendent
will check pool with you to ensure everything is correct.
Back to Table of Contents
|  |
_______________________________________________________________________________________________________________________________ |
PLASTER/PEBBLE
• A 1/2”
thick layer of plaster or pebbled finish, depending on your contract, is
sprayed and troweled onto the shotcrete surface.
• Immediately after
finish is applied, water begins filling the pool and/or spa.
• Continue filling
until water level is halfway up the tiles.
• For plaster
finish pools, begin brushing 3-5 times per day once the pool is full.
Back to Table of Contents |  |
_______________________________________________________________________________________________________________________________ |
START UP & ORIENTATION
• When your pool is full, contact the office to schedule your start up.
• Our technician will come out to get the pool up and running.
• Do not attempt to turn on the pool yourself.
• Homeowner is responsible for start up chemicals.
• Technician will orient you on equipment functionality and maintenance.
Back to Table of Contents |
_______________________________________________________________________________________________________________________________ |
FINAL WALK/PUNCH LIST
• We will walk the project with you to note any unfinished items or
necessary repairs.
• A date for repairs will be scheduled with our office.
HAVE
FUN ENJOYING YOUR NEW LAGUNA POOL!!
Back to Table of Contents |